Tender Ref.: PT/0273/2006 - Questions and Answers 4

Tender for the Design, Supply, Delivery, Installation, Commissioning, Maintenance of the Hardware, Software and Related Services for the Implementation of the Automated Vehicle Clearance (AVC) System at New Control Point for the Immigration Department

Answers to Questions 

All the information including this written response are for reference only and shall not be relied upon by the tenderers when deciding to submit their bids and/or to enter into any agreement with the Government. The Contract with the Government shall be on the terms and conditions set out in the Contract that constitutes the entire agreement between the parties to the Contract.

No.

Part

Section

Questions and Answers (Exact texts of original questions received are quoted)

01/04

VII

9.4

According to Part VII 9.4, the UPS must support each of the proposed hardware items to be installed in the resilience room for at least 30 minutes after a power supply interruption. Please clarify whether it include the mechanic motor for the checking station moving up and down. 

Answer:

As stipulated in section 9.4 of Part VII, proposed UPS must support each of the proposed hardware items to be installed in the resilience room for at least 30 minutes after a power supply interruption.

 